41. Date#
17062020
42. Objective#
To elaborate a realistic plan to continue doing experiments.
43. Method#
Look at the agreed plan from the yearly meeting.
Draw scenarios/ possibilities due to currently crisis of covid-19.
43.1. Agreed plan#
Measure the essential genes in each of the genetic backgrounds of the trajectory.
43.2. Scenarios to achieve that plan#
Scenario 1: Ideal
Overlap with Enzo and Wessel experiments
Enzo and Wessel do the SATAY on \(\Delta bem1\) and \(\Delta bem1\Delta bem3\)
Enzo will do the SATAY of \(\Delta bem1\Delta bem3\Delta nrp1\Delta bem2\)
I will do the SATAY and strain construction of \(\Delta bem1\Delta bem3\Delta nrp1\)
Scenario 2: Probable
Overlap with Enzo and Wessel experiments
Enzo and Wessel do the SATAY on \(\Delta bem1\).
Enzo will do the SATAY of \(\Delta bem1\Delta bem3\Delta nrp1\Delta bem2\)
I will do the SATAY and strain construction of \(\Delta bem1\Delta bem3\Delta nrp1\) and for \(\Delta bem1\Delta bem3\).
43.3. Consequences for each scenario#
Scenario Ideal :
Strain construction for \(\Delta bem1\Delta bem3\Delta nrp1\) (knockout the ade2 gene in ylic128)(~ 2 months). It can start in September 2020.
Do the SATAY on this strain (~ ? months)
Scenario Probable :
Develop a plan to have \(\Delta bem1\Delta bem3\) ura3- ade2-.(~ 3 months) It can start in September 2020.
Strain construction for \(\Delta bem1\Delta bem3\Delta nrp1\) (knockout the ade2 gene in ylic128)(~ 2 months). It can start in September 2020.
Do SATAY on \(\Delta bem1\Delta bem3\) and \(\Delta bem1\Delta bem3\Delta nrp1\).
44. Conclusion#
The constant in the plan is the strain construction and the SATAY on \(\Delta bem1\Delta bem3\Delta nrp1\).